Repair planning

Collision repair blueprinting checklist

Teardown revealed a broken lamp mount. A part is on order, the supplement is out, and a technician has a bay open. Your auto body production team needs to decide exactly which work can begin.

By AutoHound4 minute read
Explore a sample shopPrivate 7-day demo. No credit card.
The short answer

After teardown, bring the estimator, technician, parts lead, and production lead together around the current repair plan. Record the evidence, approvals, required parts, equipment and sublets. Release a named operation only when its dependencies are resolved. Give every hold an owner and a next review time.

Download the one-page blueprinting checklist (PDF). Take it to the parts cart after teardown. For each applicable check, mark Ready or Hold, add a reference, and give unresolved items to a named person. Mark a row N/A only after confirming it does not apply to the planned operation.

This worksheet supports the handoff into production. Use current vehicle-specific OEM information and your qualified team to determine the repair method and required operations. The intake record documents how the vehicle arrived. The final QC record documents checks on the completed work.

Establish the current scope

Start with the estimate revision the shop is working from. Match each new finding to a photo, measurement, or report and to the affected line or area. Identify who needs to review a change and whether the customer authorization covers the new work. Keep a submitted supplement and an approved supplement in separate states.

Record the procedure references the team consulted and any requirements that affect sequencing, equipment, or outside work. I-CAR describes blueprinting as an early examination that brings parts, materials, equipment, and sublet needs into view. I-CAR on blueprinting and shop workflow.

Check the next operation

  • Parts. Identify the assemblies, small hardware, and supplies needed for this operation. Confirm what is physically present, what has been verified against the repair, and which missing item changes the start date.
  • People and equipment. Name the assigned technician. Confirm the necessary bay, equipment, and relevant procedure information will be available together.
  • Outside work. For a required sublet, identify the provider, booking or dependency, expected return, and documents the shop needs back. If it happens later, record which stage must wait for it.
  • Authority and evidence. Record the customer authorization and any pending insurer response separately. State which operation the open item affects and who will verify the decision.

Work a hold through to release

In this fictional example, a technician documents damage to the left lamp mount on RO 2486. Photo P3 supports a $360 supplement. The parts lead has ordered the lamp, but the item has yet to arrive. The production lead holds the affected operation and sets the next review for Wednesday morning.

Wednesday brings the insurer’s approval and updated customer authorization. The parts dependency is still open. On Thursday the parts lead physically matches the lamp to PO 614 and records receipt. The production lead verifies the remaining checks, releases the named operation to the assigned technician, and updates the board. Two different events cleared two different holds.

Record the release decision

Write one of three outcomes on the sheet along with the reviewer and decision time:

  • Release the named scope. List the operation and assigned technician. Record the handoff on the board.
  • Release limited work. Identify both the authorized operation that can proceed independently and the operation that remains held. Have the designated lead confirm that sequence against the repair plan.
  • Hold. Record what is missing, who will resolve it, and when the team will check again. Put the blocker where the next shift can see it.

AutoHound carries the assigned staff, promise date, blocker, and parts signal on the production card. Shops can attach required checks to a stage and keep results and recorded exceptions on the RO. See how the production board works.